SNo.
|
Particulars
of items
|
Quantity
|
Perday
|
|
1.
|
Brick work in lime or cement mortar in foundation and
plinth
|
1.25cum
|
(45cuft)per mason
|
|
2.
|
Brick work in lime or cement mortar in superstructure
|
1.00cum
|
(35cuft)per mason
|
|
3.
|
Brick work in mud mortar in foundation and plinth
|
1.50cum
|
(55cuft)per mason
|
|
4.
|
Brick work in mud mortar in superstructure
|
1.25cum
|
(45cuft)per mason
|
|
5.
|
Brick in cement or lime mortar in arches
|
0.55 cum
|
(20cuft)per mason
|
|
6.
|
Brick in cement or lime mortar in jack arches
|
0.55 cum
|
(20cuft)per mason
|
|
7.
|
Half brick wall in partition
|
5.00sqm
|
(50sqft)per mason
|
|
8.
|
Coursed rubble stone masonry in lime cement mortar
including dressing
|
0.80cum
|
(30 cuft)per mason
|
|
9.
|
Random rubble stone masonry in lime or cement mortar
|
1.00cum
|
(35cuft)per mason
|
|
10.
|
Ashlars masonry in lime or cement mortar
|
0.40cum
|
(15cuft)per mason
|
|
11.
|
Stone arch work
|
0.40cum
|
(15cuft)per mason
|
|
12.
|
Lime concrete in foundation or floor
|
8.50cum
|
(300cuft)per mason
|
|
13.
|
Lime concrete in roof terracing
|
6.00cum
|
(200cuft)per mason
|
|
14.
|
Lime concrete 1:2;4
|
5.00cum
|
(175cuft)per mason
|
|
15.
|
RB work
|
1.00cum
|
(35cuft)per mason
|
|
16.
|
RCC work
|
3.00cum
|
(125cuft)per mason
|
|
17.
|
12mm (1/2) plastering with cement or lime mortar
|
8.00sqm
|
(80sqft)per mason
|
|
18.
|
Pointing with cement or lime mortar
|
10.00sqm
|
(100sqft)per mason
|
|
19.
|
White washing or colour washing coats
|
70.00sqm
|
(700sqft)per white washer
|
|
20.
|
White washing or colour washing coats
|
200.00sqm
|
(2000sqft)per white washer
|
|
21.
|
Painting or varnishing doors or windows one coat
|
25sqm
|
(250sqft)per painter
|
|
22.
|
Coal tarring or soligum painting one coat
|
35.00sqm
|
(350sqft)per painter
|
|
23.
|
Painting large surface one coat
|
35.00sqm
|
(350sqft)per painter
|
|
24.
|
Distempering one coat
|
35.00sqm
|
(350sqft)per painter
|
|
25.
|
2.5cm(1’) CC floor
|
7.50sqm
|
(75sqft)per painter
|
|
26.
|
Flag store floor laying with lime or cement mortar
excluding LC
|
10.00sqm
|
(100sqft)per painter
|
|
27.
|
Brick on edge in floor lime or cement mortar excluding
LC
|
7.00sqm
|
(70sqft)per painter
|
|
28.
|
Brick bat floor as in above
|
8.00sqm
|
(80sqft)per painter
|
|
29.
|
Timber framing sal or teak wood
|
0.07cum
|
(2.5cuft)percarpenter
|
|
30.
|
Timber framing sal or country wood
|
0.15cum
|
(5cuft)per carpenter
|
|
31.
|
Door and window shutters paneled or glazed
|
0.15sqm
|
(7sqft) per carpenter
|
|
32.
|
Door and window shutters paneled or battened
|
0.80sqm
|
(0.80sqft)percarpenter
|
|
33.
|
Sawing hard wood
|
4.00sqm
|
(40sqft) per pair of sawers
|
|
34.
|
Sawing soft wood
|
6.00sqm
|
(60sqft) per pair of sawers
|
|
35.
|
Single allahabad tiling or mangalore tiling
|
6.00sqm
|
(60sqft) per tile layer
|
|
36.
|
Double allahabad tiling
|
4.00sqm
|
(40sqft) per tile layer
|
|
37.
|
Breaking of brick ballest 40mm (11/2”) gauge
|
0.75cum
|
(35cuft)per labourer or breaker
|
|
38.
|
Breaking of brick ballest 25mm (1”) gauge
|
0.55cum
|
(20cuft)per labourer or breaker
|
|
39.
|
Breaking of stone ballest 40mm (11/2”) gauge
|
0.40cum
|
(10cuft)per labourer or breaker
|
|
40.
|
Breaking of stone ballest 25mm (1”) gauge
|
0.25cum
|
(10cuft)per labourer or breaker
|
|
41.
|
Ashlar stone dressing
|
0.70cum
|
(25cuft)perstonecutter
|
|
42.
|
Flag stone dressing
|
1.50sqm
|
(25sqft)perstonecutter
|
|
43.
|
Earthwork in excavation in ordinary soil
|
3.00cum
|
(100cuft)per belder mazdoor
|
|
44.
|
Earthwork in excavation in hard soil
|
2.00cum
|
(75cuft)per belder mazdoor
|
|
45.
|
Excavation in soil
|
1.00cum
|
(35cuft)per belder mazdoor
|
|
46.
|
Number of bricks laid by a mason in brick work upto a
height of 3m(10”)
|
600 bricks per mason
|
|
|
47.
|
Amount of work done by a mazdoor helper per day
|
||
|
Mix
|
3.00cum
|
(100cuft)mortar per mazdoor
|
|
|
Deliver brick
|
4000 nos to a distance of 15m (50”) per mazdoor
|
||
|
Deliver mortar
|
5.5cum
|
(200cuft) per mazdoor
|
|
|
48.
49.
|
Scaffolding cost for single storey building
Dressing of Soil
|
Re.0.50per cum
sq.m
|
(Rest.1.5%cuft) of brick work.
538 per mazdoor
|
Items 46,47 and 48 are based on the committee report on
rates and cost government of India.