What is IPC (interim payment certificate)?








"Interim Payment Certificates" means a payment certificate issued under the Clause "Contract Price and Payment", other than the Final Payment Certificate.

(FIDIC Conditions of Contract Definition)
Interim Payment Certificates
Most standard forms of contract state an entitlement on the part of the contractor to interim payment. These payments assist in the contractor`s cashflow, but the actual determination of the contractor`s entitlement is not made until the final certificate. The interim payments are therefore sums paid on-account of whatever the contractor might eventually be entitled to recover from the Employer. Most standard forms make the issue of a certificate a condition precedent to the contractor`s right to payment.
It is a matter of fact whether payment for work carried out is a statement of acceptance or approval. Most contract provisions for interim certification and payment are based on cumulative valuation of work done, and are only for payments on account. They are not binding nor conclusive of acceptance of the work.

Interim certificates provide a mechanism for the client to make payments to the contractor before the works are complete. The Housing Grants, Construction and Regeneration Act, states that a party to a construction contract in excess of 45 days is entitled to interim or stage payments.
Interim payments can be agreed in advance and paid at particular milestones, but they are more commonly regular payments the value of which is based on the value of work that has been completed (this is the actual value of the work completed, taking into account variations etc). The amount of these payments is entered onto an interim certificate (generally valued by the cost consultant, perhaps having taken advice from the lead designer) and the clientmust honour the certificate within the period stipulated by the contract.
If the client intends to pay a different amount from that shown on the interim certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice - see Housing Grants, Construction and Regeneration Act for more information).
The value of interim certificates is the value of the work completed, less any amounts already paid, less retention. Half of this retention will be released on certification of practical completion and the other half upon issue of the certificate of making good defects.
Interim certificates should make clear the amount of retention and a statement should also be prepared showingretention for nominated sub-contractors if there are any. The contract may require that retention is kept in a separate bank account and that this is certified. In this case, the client will generally keep any interest paid on the account.
There may be particular provision to include the value of particularly costly materials that the contractor has not yet delivered to site. This allows the contractor to order items in good time, without incurring unnecessary long-term expense, but does put the client at some risk if the contractor becomes insolvent.
On design and build projects, the amounts certified as payable may be based on a contract sum analysis
USE FULL DOCUMENTS:-